Project to cost $319 million

DAVID PUGLIESE --- Dec 07, 2017

The Canadian Special Operations Regiment will have a new compound at Petawawa in the coming years.


In total, ten buildings will be constructed in a secure compound at 4 CDSB, Petawawa. The facilities will include working space, training facilities, vehicle maintenance areas, warehouses and medical facilities. The new facilities will consolidate CSOR activities in one complex.

The entire project will cost approximately $319 million.

That amount includes:

– Project Management Costs;

– Engineering Studies;

– Design;

– Defence Construction Canada Contract Management;

– Construction (the VAST majority of the costs);

– Security;

– Furniture;

– Demolition work;

– Relocation;

– DND Communications Systems;

– HST.


All of the buildings currently occupied by CSOR will be returned to the 4 CDSB for use by other units, or for demolition. Twenty buildings are currently scheduled for demolition as they have reached the end of their economic and useful life, according to the Department of National Defence. Demolition will be contracted out separately.

Work began in July and the complex is anticipated to be completed in late 2021, said DND spokesman Daniel Le Bouthillier.

http://ottawacitizen.com/news/national/defence-watch/new-canadian-special-forces-compound-at-petawawa-to-open-by-2021
avatar
Trooper
Registered User

Posts : 949
Join date : 2017-10-07

Back to top Go down

Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum